Friday, January 25, 2013

Take your wife to work day

This is Rebecca.  I'm off work today and tagging along with my wonderful husband as he makes the rounds to check on the jobs and generally 'do his thing'.  We are at Plantation Oaks and there is lots of activity!  He has framers, plumbers and electricians all working on the same house at the same time!  I heard someone say that he can build a house fast and I definitely see how.  He's not messin' around!!




Saturday, January 19, 2013

Progress! ...despite the rain!

Despite the monsoon rains lately, the jobs at Plantation Oaks are progressing nicely.  We finished pouring the foundation on Lot 11 on Monday the 7th.  It was delayed several times, but we finally got it done.




The framing is nearly complete on Lot 14.  They've worked a lot on the weekends, and in the cold, just to avoid the rain.  The guy doing the framing is really good at what he does.  He makes very few mistakes and I almost always have materials left over.  I've used him for the last few houses and I plan to use him for Lot 11.  He'll move over there and get started as soon as Lot 14 is done.  Time is money for the customer now that the first draw has been made on the construction loan.  The pressure is on the make sure the schedule flows smoothly and there are is no downtime. 





The progress is easy to see at this stage



Tuesday, January 1, 2013

More rain!

We need the rain, but why does it always come when you have something planned outdoors?  We are nearly ready to pour the slab on Lot 11 and now have rain delays. Thank goodness for plastic.

My wife snapped this shot as I checked on the progress.