At this stage of the home construction, things seem to go very quickly. We finished the brick on the exterior of Lot 14 and added a white slurry to accent the front. On the inside, we have hung and textured the drywall. Cabinets and trim arrive this week.
The progress on Lot 11 is about 2-3 weeks behind Lot 14. We are still completing the framing. The electricians, AC crew, plumbers and a few others have been hard at work.